Nairobi says it has chosen a station contractor. What comes next?

Kenya Railways says contractor and engineer procurement is complete, but station financing is still open. Early 2027 is the funding target, not a construction date.

Timeline from the 2022 Railway City groundbreaking through the 2023 design contract and November 2026 procurement update, with early 2027 identified as a financing target.
Town Desk News original illustration

Kenya Railways says it has completed procurement for the contractor and supervising engineer for a new Nairobi Central Station and its surrounding public spaces. The work still needs financing. Railway officials are targeting early 2027 to close those arrangements, not promising that construction will start then or that passengers will see a new timetable.

Managing Director Philip Mainga gave the update during a Nov. 19 meeting in Nairobi with British development minister Kirsty McNeill. Kenya News Agency reported that Kenya Railways is working with the National Treasury and other agencies on the financing. The talks also covered UK-funded technical assistance and ways to attract investment for the surrounding Railway City development. Kenya’s Standard and People Daily separately reported that financing remained outstanding even though the contractor and supervising engineer procurement had been completed.

The accounts reviewed for this story did not identify the construction contractor or publish an award notice or contract. That distinction matters: Kenya Railways has publicly identified a firm on a different part of this project. The railway says it signed a central design contract with WS Atkins International Limited in June 2023. That was a design agreement, not evidence that the firm won the construction procurement discussed this month.

Why this is not the first groundbreaking

President William Ruto presided over a Railway City groundbreaking in December 2022. Kenya Railways said in February 2023 that early works had begun and identified a pedestrian footbridge over the railway yard among the first phase’s planned elements. The November financing target concerns the new station and its surrounding public spaces. It isn’t a second announcement that all work on Railway City is starting from scratch.

A 2025 Kenya Railways procurement document shows what the station work was meant to cover. The invitation called for a new station building at the north entrance, two bridges spanning the new platforms and work on the passenger platforms. It also asked the contractor to develop a phased construction plan that accounts for continued freight and passenger operations. Those are requirements in a bid document, not a published disruption schedule or a guarantee that the final layout will match every preliminary detail.

One railway station, a much bigger district

The station sits inside a 438-acre redevelopment plan for central Nairobi. In October, Kenya Railways described separate areas for markets, housing, the station and a convention and events district. The affordable housing area alone spans about 112 acres in that plan. That figure is an area earmarked in the plan, not a count of homes started or a commitment about when residents could move in.

Railway officials told Kenya News Agency they expected work on the separate convention and events development, including a multipurpose arena, to begin in the coming weeks. No firm start date was given. Even if that work begins, it would not show that financing had closed for the rail station.

For commuters, the next milestone is a public announcement that station financing is complete, followed by a construction timetable and any separate rider notices. This month’s talks established none of those dates, and they did not announce any changes to existing trains.

Sources & reporting notes

  1. Kenya News Agency: account of the Nov. 19 meeting

    Direct statements from Mainga, meeting scope, open financing, early 2027 target and separate convention project.

  2. The Standard: local reporting on the financing talks

    Independently covers the public reporting; the account reviewed does not publish the construction contractor’s name or award notice.

  3. People Daily: contractor procurement and financing target

    Independently covers the public reporting; the account reviewed does not publish the construction contractor’s name or award notice.

  4. Kenya Railways: design contract signed in June 2023

    Distinguishes the separately announced designer from today’s construction procurement and financing.

  5. Kenya Railways: February 2023 early works announcement

    Distinguishes historical groundbreaking and early works from today’s construction procurement and financing.

  6. Kenya Railways’ 2025 design and construction invitation

    Pages 6–7: preliminary scope and continuity planning, not final designs or a service notice.

  7. Kenya Railways: October stakeholder planning update

    District and housing precinct areas and examples of precincts.