PATCO’s 2027 budget puts Camden County tracks and platforms on the list
The bridge authority approved $5 million for elevated track structures in Collingswood and Westmont, and $3.5 million for Woodcrest platforms.

PATCO riders in Camden County can look for work on the elevated tracks in Collingswood and Westmont and at Woodcrest Station in Cherry Hill. The Delaware River Port Authority’s 2027 capital budget sets aside $5 million for the structures under the elevated tracks and $3.5 million to continue work on the Woodcrest platforms.
The authority’s board approved the budget on Nov. 18, 2026, as part of an $802.7 million five-year program covering the PATCO rail line and all four of its bridges. The 2027 portion totals $178.7 million in planned DRPA spending across 181 projects. The authority expects about $30.45 million more from state and federal grants.
The 2027 rail budget also includes $35 million for track and for the points where trains switch between tracks, plus $3 million for drainage, embankment and retaining-wall work. The announcement does not give start dates for the projects or say when riders might see schedule changes.
On the bridges, the five-year plan sets aside $255 million to protect piers on the Walt Whitman and Ben Franklin bridges from vessel strikes, with $500,000 in 2027 to advance design. Separately, the five-year plan includes $80 million to resurface the Ben Franklin Bridge deck and repair expansion joints, with $15 million in the 2027 budget.
The board is scheduled to take up the DRPA and PATCO operating budgets separately on Dec. 9. The Nov. 18 decision was about capital spending; the announcement did not announce fare or toll changes.
Sources & reporting notes
- Board decision
DRPA: approved five-year capital program and 2027 budgetConfirms the Nov. 18 vote, annual and five-year totals, project allocations and Dec. 9 operating-budget vote.
- Rider information
PATCO schedules and temporary service changesUse the current schedule for travel, not the capital-budget announcement.
- Station information
PATCO: Woodcrest StationConfirms Woodcrest is in Cherry Hill, Camden County.