Business · Burkina Faso

A new permit for Burkina Faso’s Perkoa zinc mine. When could production return?

Burkina Faso approved a new permit for Perkoa, where mining stopped in 2022. The cabinet outlined planned investment and production but did not give a restart date.

Timeline showing Perkoa mining suspended in 2022, the old permit withdrawn in 2023 and a new permit approved in 2026.
Town Desk News original editorial timeline illustration. Generic mine line art is not a depiction of Perkoa’s current condition or proof of activity.

Burkina Faso has approved a new industrial mining permit for the Perkoa zinc mine, more than four years after a deadly flood stopped extraction. The Nov. 19 cabinet decision gives a state mining subsidiary the permit. It does not mark the start of mining, and the government’s published decision did not say when extraction could resume.

The permit goes to SOPAMIB Perkoa SA, part of Burkina Faso’s state mining participation company. The mine is in the commune of Réo, in Sanguié province in the Nando region. The Nov. 19 cabinet minutes put planned investment at 37 billion CFA francs.

The government estimates the mine could produce 576,000 metric tonnes of polymetallic concentrate over an estimated four-year operating life. That is a projection for the whole project, not an annual target or a measure of pure zinc. The four-year figure describes expected mine life, not a countdown starting with the permit.

The cabinet also projects that the project would create or sustain 400 direct jobs and about 850 indirect jobs. Burkina24’s local coverage noted that the years-long halt had cost jobs and reduced tax and customs receipts, as the cabinet’s record described. The new projections are not a hiring announcement.

Nantou Mining Burkina Faso previously held the permit. Industrial extraction was suspended after the April 16, 2022 disaster, according to the cabinet. Afrik.com reported that flooding trapped and killed eight workers. In November 2023, a separate cabinet decision recorded the withdrawal of Nantou’s permit and said the company was in judicial liquidation and lacked the funds to restart the mine.

Afrik.com said restoring flooded underground workings would be one obstacle before extraction could return. The Nov. 19 decision did not set out a timetable for that work or announce that the mine had passed a new safety review. For now, the document confirms who has the permit and what the government expects if the project goes ahead, not when Perkoa will produce again.

Sources & reporting notes

  1. Burkina Faso cabinet record, Nov. 19, 2026

    Printed pages 12–13, section I.8: permit, operator, geography, suspension date, planned investment and whole-project projections. No confirmed production/restart date. Budget-contribution amounts omitted.

  2. Cabinet record, Nov. 8, 2023

    Section I.2 records withdrawal of Nantou’s permit, judicial liquidation and lack of funds at that time.

  3. Burkina24 local coverage, Nov. 20

    Coverage of the cabinet decision, not independent proof of a reopened or producing mine.

  4. Afrik.com regional reporting, Nov. 21

    Attributed reporting on the eight deaths in the 2022 flood and the underground rehabilitation obstacle; not a current safety review or restart announcement.